Progress of Construction Works

Lot 1

The official Commencement date was on 18.05.2020.and deadline for completion is 18.01.2022.

Lot 2

The official Commencement date was on 14.10.2020. deadline for completion is 16.06.2022.

Site activities at SS Kraljevo 3 started on 22.02.2021. At this point, following activities were performed:

  • Construction of Access road;
  • Construction of site office plateau;
  • Installation of site offices;
  • Demolishing of barrack;
  • Installation of temporary gate;
  • Installation of construction fence;
  • Levelling of plateau 400 kV;
  • Excavation for primary equipment and gantries foundations;
  • Excavation and dismantling of existing 10 kV cable.

Site activities at SS Kragujevac 2 started on 01.03.2021. At this point, following activities were performed:

  • Construction of Access road;
  • Construction of site office plateau;
  • Installation of site offices;
  • Excavation for primary equipment and gantries foundations;
  • Excavation for relay house;
  • Reinforcement assembly.
Back To Top
Panerai Replica Patek Philippe Replica Rolex Replica Richard Mille Replica Watches Ulysse Nardin Replica Rolex Air King Replica Rolex Sea-Dweller Replica Rolex Datejust Replica Rolex Day Date Replica Rolex GMT Master Replica www.rabanwatch.com Color Shift Vinyl Wraps Metallic Vinyl Wraps Carbon Fiber Wrap Diamond Car Wraps White Vinyl Wraps www.vinylcarwrapshop.com