
Progress of Construction Works
Lot 1

The official Commencement date was on 18.05.2020.and deadline for completion is 18.01.2022.
Lot 2
The official Commencement date was on 14.10.2020. deadline for completion is 16.06.2022.
Site activities at SS Kraljevo 3 started on 22.02.2021. At this point, following activities were performed:
- Construction of Access road;
- Construction of site office plateau;
- Installation of site offices;
- Demolishing of barrack;
- Installation of temporary gate;
- Installation of construction fence;
- Levelling of plateau 400 kV;
- Excavation for primary equipment and gantries foundations;
- Excavation and dismantling of existing 10 kV cable.
Site activities at SS Kragujevac 2 started on 01.03.2021. At this point, following activities were performed:
- Construction of Access road;
- Construction of site office plateau;
- Installation of site offices;
- Excavation for primary equipment and gantries foundations;
- Excavation for relay house;
- Reinforcement assembly.