Progress of Construction Works

Lot 1

The official Commencement date was on 18.05.2020.and deadline for completion is 18.01.2022.

Lot 2

The official Commencement date was on 14.10.2020. deadline for completion is 16.06.2022.

Site activities at SS Kraljevo 3 started on 22.02.2021. At this point, following activities were performed:

  • Construction of Access road;
  • Construction of site office plateau;
  • Installation of site offices;
  • Demolishing of barrack;
  • Installation of temporary gate;
  • Installation of construction fence;
  • Levelling of plateau 400 kV;
  • Excavation for primary equipment and gantries foundations;
  • Excavation and dismantling of existing 10 kV cable.

Site activities at SS Kragujevac 2 started on 01.03.2021. At this point, following activities were performed:

  • Construction of Access road;
  • Construction of site office plateau;
  • Installation of site offices;
  • Excavation for primary equipment and gantries foundations;
  • Excavation for relay house;
  • Reinforcement assembly.